"Great to get back to Aberfeldy after 5 weeks away and see the amazing progress on the cinema refurbishment: new roof in place, auditorium walls up, space created for beautiful new floor to ceiling windows looking out on to Chapel Street and the Square. Lots of activity by the builders to make sure that we all meet the deadline of end February for completion. Then it will be just a few short weeks before the cinema will open around Easter. Can't wait! Keen to get views from everyone in the community about what kind of film and alternative content they would like to see in the programme so that we can pass them on the to Cinema Manager who should be in post by the first week of December. Please send your ideas to: info@birkscinemafriends.org.uk
Wednesday, 31 October 2012
Window on the Square
Friday, 3 August 2012
Behind the scenes..
Summer is speeding by – and so much is happening ‘behind the
scenes’ at the cinema. We have got to
that stage where from the outside it might look like very little is happening –
but actually we are busy busy getting things in place.
Hadden’s are making brilliant progress inside the building;
the amazing cooling labyrinth is in place – a whole series of pipes laid in
concrete under the auditorium – accessing the well of ‘coolth’ under the
building, so that on those fine summer days when we need the auditorium to be a
little cooler – we draw cool air from deep below the floor. Altogether, really cool. But now that the pipes are buried in
concrete – they will never be seen again!
The foundations for the internal walls and a solid floor
screed – so we are beginning to see the shape of what is to come. Very, very exciting.
During August the roof will be replaced – and this requires
scaffolding around the entire building, which unfortunately means that the
Chapel St bus stop will need to be temporarily moved for the next ten to twelve
weeks. Our apologies for any
inconvenience caused by this.
The other really exciting development has been the creation
of The Birks Cinema Ltd. This is now an
incorporated company (SC428528) and we have a board of nine Directors; three
from FoTBC and six new people. The new Trading Board members are:
Karen Banyard
Patti Walker-Booth
Ron Dekker
Mike Dukes
Charlotte Flower
Peter Guthrie
Daniel Maslen
Kevin Ramage
Douglas Swan
We have had our first full Board meeting, and what an
amazing room full of local expertise, enthusiasm and experience.
And elsewhere? This
is an exciting time for cinema in Scotland – The Thurso Cinema (http://thursocinema.co.uk) reopened in July and Oban Phoenix Cinema (http://www.facebook.com/pages/Oban-Phoenix-Cinema)
is re-opening in August. Good luck to them both and Vive le cinema!
Other news:
The AGM of the Friends of The Birks
Cinema takes place on 30th August at Dewars Distillery from 730pm.
Recruitment of a General Manager of
the Birks Cinema will begin in mid-August. Please see the Birks Cinema website
for a link to the advert and further details, go to: www.birkscinemafriends.org.uk
Wednesday, 11 July 2012
... and the walls came tumbling down
Time is just flying by and work is progressing in the office and in the cinema itself. I've been busy submitting claims to funders for reimbursement of invoices received, preparing and updating cashflow projections and creating systems to ensure efficient and effective management of the funds for the refurbishment project. I need a holiday now!
You may have seen a brief clip on BBC Reporting Scotland showing the digger in the cinema building. This was to remove wooden and concrete
floors as well as ground floor walls. The existing foundations have been found to
be in a sound condition and this has enabled work to progress. The first concrete for the foundation has been poured around the inside of the existing walls
incorporating all services ducts and this has passed Building Control
inspection.
I believe the next step is to lift the roof! Hope it stays dry long enough.
Monday, 4 June 2012
Well, I've been in post now for just over 2 weeks and I thought I should introduce myself. My name is Angela Hanvey and The Friends of The Birks Cinema have contracted me as Financial Co-ordinator to oversee the administration of funds during the refurbishment process. I've lived in the Tay Valley area for more than 13 years and love this part of the country. From a work perspective I bring with me to this post a wealth of experience from business, charities and the public sector.
What a privilege it is to be part of this fantastic project to bring life back into the old cinema building and, what's more, to bring it back to life as a community cinema. You'll see that work has now begun and over the next few weeks and months we'll keep you updated on progress. We have also managed to get the office up and running in the Locus Centre where I am based. We're now fully functional and enjoying the views over the rooftops.
Several meetings have taken place over the last few days, most importantly with Ronnie Horne, Anne Nicol and Bob Cobban of Hadden Construction Ltd near Perth; SGRIPD, who will process our claims for funding from Scottish Rural Development Programme; and our Quantity Surveyor, Alan Smith from Ralph A Ogg . All of these meetings were interesting and very informative and hopefully I've climbed someway up the steep learning curve.
We now await with trepidation the work programme and cashflow projections from Hadden early this week.
What a privilege it is to be part of this fantastic project to bring life back into the old cinema building and, what's more, to bring it back to life as a community cinema. You'll see that work has now begun and over the next few weeks and months we'll keep you updated on progress. We have also managed to get the office up and running in the Locus Centre where I am based. We're now fully functional and enjoying the views over the rooftops.
Several meetings have taken place over the last few days, most importantly with Ronnie Horne, Anne Nicol and Bob Cobban of Hadden Construction Ltd near Perth; SGRIPD, who will process our claims for funding from Scottish Rural Development Programme; and our Quantity Surveyor, Alan Smith from Ralph A Ogg . All of these meetings were interesting and very informative and hopefully I've climbed someway up the steep learning curve.
We now await with trepidation the work programme and cashflow projections from Hadden early this week.
Monday, 21 May 2012
and,,, Action!
Just towards the end of last week Haddens put
fencing up around the building and at last it feels we are on our way. So much
has happened over the last few weeks but none of it was 'visible'. I was at
Logierait Market on Saturday and so many folk came up to say how delighted they
were to see building activity around the cinema.
What else has been happening? Our team has
expanded, and a big welcome to Angela Hanvey, our wonderful new Finance
Adminsitrator, started this week. She will be working with us to ensure that
all the grant funds are administered in good time - paying our bills and
reporting as needed to funders.
And of course we had a visit from the Screen
Machine, a foretaste of things to come. One of the things I love about going to
the Screen Machine is that you are bound to see someone you know in the
audience; there is always great chat before the film starts, a real buzz to the
place - whether catching up or anticipating the film, or discussing the film
seen the day before - the chatter is loud and lively.
We hope to have three or four more visits of the
magic lorry before The Birks Cinema opens next year - so keep looking out for
the posters.
Thursday, 10 May 2012
Good bye to the old building
Hello, Charlotte Flower here,
and I will kick off the Blog
Today, the builders moved
in. This is a milestone that like so
many others over the last few years passes with no great fanfare. For many this is just a statement of
fact. For me though and others involved
in this long campaign – it is momentous.
A day I have often not really allowed myself to imagine.
I missed the Open Doors on
Saturday but was keen to go in and say ‘Goodbye and Good luck’ to the Old
Birks. I have this cinematic image in
my head; closing the door on the old and opening it to the new! Just like that! If only life were that easy!
I am so glad I went
in. The building is empty now; all the
paraphernalia that has drifted in over the years has been removed. Just a quiet echoing expectant space.
With no one else there to
disturb me, I embarked on something that I have tried a few times before to do
– but never really managed. But this
morning it felt very real. As I have
seen the Architects plans so often, I can walk through the empty building and
‘know’ where the walls, doors, reception desk, etc are. So I decided to ‘walk to my seat’;
visualising the experience as I walked across the empty space.
So,
walking from the front door and into the building, I visualised the reception
desk and counter; for a moment I
wondered if I should go left towards where the ATM would be to pick up
prebooked tickets, but then changed my mind and went straight to the
counter. I bought my ticket and then a
cup of coffee; I took this into the café area and sat for a moment, enjoying
the bustle and chatter of the café, looking out onto the Square watching the
world go by. Then, time to take my seat
– I made my way to the auditorium; I climbed the steps to the back and found my
seat. Sitting back, I waited for the
lights to dim, the chatter to still and the show to start.
This time, this whole
imaginary experience felt almost tangible and real. I don’t need to hold my breath and hope. The builders (and I met the lovely Finlay
this morning) are going to transform the building and every time I have a
chance to walk through these doors over the next few months, our dream will be
ever more close.
So, as we move forward, I
hope you might find interest and pleasure in this blog, as we share our journey
with you. And please do join in.
Birks Cinema - the work begins
9th May
The builders move in today
and very soon the building will be wrapped up inside protective layers of
scaffolding and fences. Just like a
chrysalis inside a cocoon, it will emerge resplendent in 10 months or so. Over this time, we won’t have the Open Doors
opportunities to share progress but we really don’t want people to lose sight
of the project. So we have a number of
ideas to keep the cinema visible to everyone and in your thoughts – the display
in MiSwaco window is one, and this blog is another
Through the blog we can
provide a more personal view of the development – and it is our intention that
we will share the load within the Committee – but also it would be great if
readers added their own thoughts and stories.